If the best operating level of a piece of equipment is at a rate of 400 units per hour and the actual output during an hour is 300

If the optimal operating level of a piece of equipment is 400 units per hour, but the actual output during an hour is only 300 units, what is the capacity cushion?

A. 25 percent
B. 100 units per hour
C. 75 percent
D. 125 percent
E. 133 percent

7 Answers

A
Anonymous

Feb 13, 2025

The correct answer is A.Explanation:Giving the following information:The best operating level of a piece of equipment is at a rate of 400 units per hour and the actual output during an hour is 300 units. To calculate the capacity cushion, we need to use the following formula:Capacity cushion= spare capacity/ total capacityCapacity cushion= 100/400= 0.25=25%
A
Anonymous

Feb 16, 2025

#1 Windows#2 Ubuntu#3 Mac OS#4 Fedora#5 SolarisThose are the top 5 best operating systems
C
Cordie Rowe I

Feb 12, 2025

d. 70%Explanation:It is best that the Operating point be around 70%. The Operating Point is the ratio between the Number of Customers served per period (Mean Service Rate) to the number of customer Arrival per period (Mean Arrival Rate). As the text says, it is better that Mean Service Rate exceed the Mean Arrival Rate and that the Mean Arrival Rate should not get too close to the Mean Service Rate. This makes 70% the best choice as Mean Arrival Rate is both less than and not too close to the Mean Service Rate. Also, it would be better to have the Mean Service Rate at 70% because it would keep the servers/ waiters enough work to do but at the same time they can cater to new arrivals efficiently. If the Mean Arrival Rate was more than the Mean Service Rate, more people would be arriving than the Servers can serve. This can lead to mistakes and neglect of customers. For these reasons, 70% is the best option. If you need any clarification do react or comment.
A
Anonymous

Feb 04, 2025

25%Explanation:Given:Projects done by first worker per day = 1.5Projects by second worker per day = 2Projects by third worker per day = 3Projects by fourth worker per day = 1.5Actual projects completed per day = 2Now, Capacity utilization = orCapacity utilization = orCapacity utilization = orCapacity utilization = 0.25 = 25%
A
Anonymous

Feb 03, 2025

C. 1.25Explanation:Mathematically;Capacity utilization rate= actual output per hour / operating level rate per hourActually output per hour= 500unitsOperating level rate per hour= 400Hence,Capacity utilization rate= 500/400Capacity utilization rate= 1.25
A
Anonymous

Feb 03, 2025

False.Explanation:The given statement would be categorized as false as it asserts as inappropriate claim regarding the calculation of 'capacity utilization rate'. Capacity utilization rate aims to measure the literally realized proportion of potential/probable economic output. It is calculated by actual output being divided by the maximum possible output which is further multiplied by 100. Thus, it is written as:{Capacity Utilization rate = "(Actual output/Maximum possible output)*100"}Therefore, the given statement would be categorized as false.
B
Bridget Lakin

Feb 11, 2025

The correct answer is letter "D": seeks to deliver superior value to buyers by satisfying their expectations on key attributes and beating rivals in meeting customer expectations on price. Explanation:Best-cost provider is a strategy by which suppliers attempt to provide consumers with high-quality products using methods of production that reduce costs. By doing so, suppliers would give more value to the money of their customers while meeting their expectations on the product purchased at the same time.As production costs are lower, suppliers would be generating a comparative advantage.

Want to answer this question?

Join our community to share your knowledge!

Related Questions

8
CSS stands for Cybernet Slash Support or Cybernet Software Systems ?

What does CSS stand for: Cybernet Slash Support or Cybernet Software Systems? I came across a company located in T. Naga...

3
Find the circumference of p. leave your answer in terms of pi. the radious is 5 in.

Find the circumference of a circle with a radius of 5 inches. Please express your answer in terms of pi.

3
how tall is 77 inches in feet?

How tall is 77 inches when converted to feet?

3
In circle O, ST is a diameter. What must be the value of x?

In circle O, ST is a diameter. What is the value of x if (2x + 8) equals one of the following options: 22.0, 25.0, 25.4,...

2
a question regarding torque in a magnetism setting?

I have a question regarding torque in a magnetism context. I understand that the equation τ = IABsin(θ) will be relevant...

2
Find the cube roots of 8(cos 216° + i sin 216°).

Could you please help me find the cube roots of the complex number represented in polar form as 8(cos 216° + i sin 216°)...

1
Present and future values for different interest rates find the following values. compounding/discounting occurs annually. round your

Please find below the present and future values for different interest rates. Compounding and discounting occur annually...

3
Why do all shareholders agree on the same goal for the financial​ manager? ?

What is the reason that all shareholders tend to agree on a common goal for the financial manager?

1
A radio telescope has a parabolic surface as shown below. If the telescope is 1 m deep and 12 m wide, how far is the focus from the vertex?

A radio telescope features a parabolic surface, as illustrated below. Given that the telescope is 1 meter deep and 12 me...

5
Career Explortion Help? (earn 10points best answer) – help soon. thx you! :?

According to the United States Business Administration, which section is considered the most crucial part of a strategi...